Week ending 24th June

Monday

 – eight members appeared on site where a number of tasks were started and many completed.

Finish off bridge pedestrian shuttering west side

                                             

Ffitting of single gauge point blade

                                             

Teram to junct and transfer of ballast by wheelbarrow.

                                              

Stan

Thursday

 – before lunch the team on site made huge inroads into clearing debris and logs from the steaming lie car park area.  Circuit B panel building continued, as did work on the first two Oban points, and the edge boards east of the first crossing were completed.

James