Week ending 20th May

Thursday

 – relatively modest turn out this week, but managed to get a range of tasks done.

The car park being relatively empty car park allowed the felling of two trees behind the east abutment of the bridge, the trunks being pulled away from the bothy and station with the aid of PN’s tractor.

  

Work continued on the rails for the second level crossing and further progress made on the 7¼ / 5in panels.

 

James’ digger, driven by RW did sterling work spreading out soil for the picnic area whilst a small team tilled the clay on the sides of the east cutting in preparation for seeding with microclover.

 

Meanwhile, David Heath continued his meticulous journey laying panelling along Circuit B.

Paul K