Week ending 24th June

Monday  – eight members appeared on site where a number of tasks were started and many completed. Finish off bridge pedestrian shuttering west side                                               Ffitting of single gauge point blade                                               Teram to junct and transfer of ballast by wheelbarrow.                    Read more about Week ending 24th June[…]

Week ending 17th June

Thursday  – today saw felling work restart for the steaming lie access road. On the track front, Circuit B panel assembly continued and more rails were rolled for 2 panels of Circuit C in the 4-track area. Also more progress on the first two Oban points.                                       

Week ending 3rd June

Thursday In the morning the Comrie panels stored outside were moved with the help of the digger from the outside assembly area to beside the containers. In the afternoon work was done to remove material from the intended location of the south west junction.                                         In parallel panel assembly continued Read more about Week ending 3rd June[…]